During dry-dock in Marseille France we have removed the old silences and the exhaust and it was installed 3 scrubbers and complete exhaust till the funnel.
The top of Aluminium funnel was cutted and temporary removed in order to fit the scrubbers and exhaust.
The job was done under CNM shipyard.
Job was performed in 2weekes with over 45 persons involved.
Job done in October 2017.